Day 6 was a bit underwhelming, though necessary:  underwriter came to inspect the wiring.  It passed.

Day 7 was a bit underwhelming … very little construction.

Day 8 was productive.  Dry wallers came for a visit to make the exposed walls a bit more tidy and ready for the eventual cabinets.

New Butler’s Pantry … temp home for the dog to eat.

 

 

Butler’s Pantry entrance with new headers

 

 

More fresh dry wall

The Kitchen with new dry wall.

 The electrician was back today.  Lots of wiring.

 

 The line to the ovens hangs in our basement

 

 

The old pantry/new butler’s panty ceiling.  The lone CFL looks sad.

 

The plumbing was smooshed up to be smaller.  New cabinets reach the ceiling. 

The outlet for our new, planned, to be decided mini-chandelier.  Covered over is the old fixture for our ceiling fan.

    